Gordon Road will remain closed to thru traffic. Residents who live on Gordon Road between US-10 and Hansen Road will have access to their property.
HMA paving is scheduled for Thursday June 27th weather permitting. The first layer of HMA will be completed in 1 day. The MCRC crews will continue working on the shoulders of the roadway. The second layer of HMA is tentatively scheduled for mid-week next week.
Please be careful when driving and approaching workers and construction equipment. Make sure the equipment operator sees you before you get close to him.
The MCRC has signs and barricades set up to warn motorists about the construction project. The project is anticipated to be substantially completed by July 3rd, 2024. The MCRC & Amber Township appreciates your patience and cooperation during this project.
Traffic should seek alternate routes when possible.